Introduction

The 57 acres that comprise Cedar Ridge Farm are located in the beautiful rolling hills of South Central Kentucky. My wife, our four children, and I are on a homesteading adventure as we work toward increased self-sufficiency. We grow much of our own food and enjoy being in touch with the agrarian roots of our lives.

One of the major projects we have undertaken is the building of our own home. The house we're building has three major distinguishing features: 1. we're building it without incurring any debt; 2. it is a timber frame structure; and 3. the exterior walls will be plastered straw bales. We live debt and mortgage free, and building our house with that approach makes perfect sense. Large timbers in a home possess a beauty and project a sense of strength, stability, and warmth that we want in our home. Straw bale walls provide insulation and make ecological sense. This blog is a record of our home-building project.

Monday, June 22, 2009

The block-work continues

    It’s been hot and humid the last few days. Yesterday’s temperature was somewhere around 93 degrees, or so I was told. I don’t have a thermometer with which to measure the temperature. I do know that it was hot while I worked – I was drenched with sweat. But, that’s to be expected, and it’s not a problem.

Yesterday morning, I finished mortaring the rest of the blocks for first course of the crawlspace wall. south wall from east endThere was about 80% of the back wall to be completed, and it went pretty well.

After finishing the mortaring, I started laying blocks on the front. After about 50 blocks, it was lunch time and time for a dry shirt. After lunch, I continued laying block along the front of the house. It wasn’t long until my shirt was soaked again. I hauled six blocks at a time in the wheel barrow to the corner of the house and set those before getting another load. Meanwhile, my boys hauled two blocks at a time (working together) to stack them on the east side of the house. That way they’ll be ready when I start laying the blocks on that side and the back of the house.

south wall from west endAbout ten feet from the west end of the front wall, I set an access door in the wall. I bought a 32” x 32” door on Friday. These doors are designed to be installed in a mortared wall in which the heights and widths are figured in multiples of eight inches. When dry stacking concrete blocks, you aren’t working with multiples of eight. The blocks are 7-5/8” tall and 15-5/8” long. So, my 32” x 32” door wouldn’t fit perfectly in a two block wide by four block high space.

access doorIt wasn’t a problem though. Because I am laying the blocks on each of the four levels independent of the other levels, it wasn’t a problem to bring the front wall from the east side to the door and then start the next section from the door to the west end. Height wise I wasn’t concerned, because I planned on using the sill for the top of it.

I mortared two four inch high solid concrete blocks onto the first course of blocks where I wanted to put the access door. Using a masonry blade in my circular saw, I cut into the ends of two blocks for the bottom plate of the door frame. It’s made to be mortared between courses which wasn’t going to work for me anyway. Once I set it up four inches on the solid blocks, it also put the bottom plate in the middle of the next course of blocks. It fits nicely in the cuts on the blocks, and they help hold it securely.

The top of the door frame is two inches below the top of the block wall. Once I place the sill on top of the wall, I’ll attach a two inch piece to it above the frame. I’ll also come back and caulk the seams around the frame from the inside to make it tight and secure. I don’t want air gaps around it.

The wall along the front came out acceptably well. It looks good with it there. It’s really nice to see progress on the house, but it sure is a lot of work. I’ve got to get the other walls blocked and then coat all of them. I’ll probably soak a few more shirts before I’m done.

House with front crawlspace wall

Thursday, June 18, 2009

Blocking in the crawl space

We’ve had plenty of rain so far this year. The garden has not suffered from dryness. In between rain showers and storms and all the other work there is to be done around here, I have continued to work on the house. I laid out blocks on the footer last week, figuring where the crawlspace walls need to be in relation the house frame.

011Earlier this week, after some rain and before some other rain, I started mortaring the first course of blocks on the west side of the house for the wall that will be under the mudroom. The first step in the process was to remove some of the accumulated mud that had been deposited around the blocks by the rain. Then, I lifted out the block that was to be mortared into place, and placed some mortar where the block had been.

012After distributing the mortar where the bottom edge of the block would set on it, I placed the block back into position. The main purpose for the mortar is to get the first course of blocks level. So, after placing the block on the mortar, I used a piece of wood to get it into place and then checked its placement with a level. I endeavored to make sure that each block was level side-to-side and along the line with the other blocks.

016015

It takes a while to mortar the first course of blocks into place. I was able to complete the ones on the level that will be beneath the mudroom.  It then rained off and on during the next couple of days, and I managed to work on some other things that needed done.

018

I was able to return to the project yesterday afternoon after spending the morning working on my class (I teach a class online for a university). I started by mortaring the blocks along the next level of the footer on the west side of the house. This is a shorter run than the previous level, and it went fairly quickly.

After getting these blocks mortared into level, I began laying blocks. One thing about dry stack concrete block construction is that the block-laying goes quickly. I had to haul the blocks from where I had the block company put them a few weeks ago which is maybe 20 yards away and down hill from the house. I moved six at a time using a wheel barrow. That seemed to work better than using a hand truck.

I began laying blocks for the walls under the mudroom since that mortar was fully set up and cured. After completing laying those, I went ahead and laid the ones on the section I had just mortared. I figured that the mortar wasn’t going to settle or move with the weight of the blocks anyway.

Because of the way I designed and poured the footer, there are four levels for the blocks around the house. I did not worry about making the steps for each level perfect with the other levels so that the blocks could 026be laid seamlessly all the way around the house. Each level can be constructed as a separate wall. Any gaps that may exist between levels will be filled with concrete. Then, the whole thing will be coated with surface bonding cement. I will cut cedars for the sill on top of the wall, so any variation in height will be accounted for in the dimensions to which I cut them. This simplified the figuring and block laying for me.

I saw a block wall a couple days ago for which the footer appeared to have been poured on an angle matching the slope of the house site. The blocks appeared to have been cut along the bottom so that the top would be level. I didn’t want to do that much cutting. I think my method will work all right.

025In anticipation of plumbing that I’ll do later, I cut a hole in one block before laying it. This hole will allow me to run the sewer pipe to the septic tank through the wall. I am not completely sure where the septic tank will go at this point. So, I’ll cut another hole on the opposite side of the house, too, just in case I need to place it on that side. I knew I didn’t want to cut a hole later.

022As can be seen in the photo to the left, I didn’t lay out the end wall on the cellar exactly right. It doesn’t line up straight with the crawlspace wall I just laid. I can’t change it, of course, and it really won’t create much problem. I expect that it won’t be very noticeable later anyway.

A thunder storm rolled through just after I started writing this post. I was planning on working on the front crawlspace wall this afternoon. It may be too muddy now. I’ll see in a little while.

 

      021  024033

Tuesday, June 2, 2009

Perimeter footer

With enough rain-free weather, I was able to complete the forms for the perimeter footer on Tuesday of last week. There are four levels for the footer because of the slope of the house site. I didn’t want to excavate the trench for the footer the same depth all the way around the house.

footerOn Wednesday morning, I called the local ready mix concrete company to order four yards of concrete. They were able to bring it out right away. It didn’t take long to pour the concrete. Dad and I screeded it which also didn’t take long. The footer is 14 inches wide, 8 inches thick, and has two 5/8” rebar pieces in the middle.

About an hour after we finished, a small rain storm came through. It didn’t dump much rain, but what rain that did fall fell hard. The concrete hadn’t had enough time to set up hard enough not to be affected by the rain. exposed aggregate because of rainThe main effect was that some of the cement and sand on the surface was washed away, leaving the courser aggregate exposed and loose on top. This occurred most dramatically to the footer at the front of the house because the runoff from the roof on that side hit directly on the outside quarter of the footer. You can see in the photo to the right the effect it had. It won’t really matter, though. The first course of blocks will be set onto the footer with mortar, and, once the walls are finished, the footer will be covered with dirt, never to be seen again.

footerfooter

I will begin laying the blocks this week as time allows. There are a lot of other jobs to be done around our homestead and we’ll be having some visitors for part of the week and next weekend (one of Anne’s sisters and her family).

Looking ahead to the order of construction, once the blocks are laid, it will be time to start framing the porch. I’ll have to pour footers for under the porch posts, lay blocks for the piers, and frame the porch deck. At that point I will put down the first floor subfloor, including under where the straw bales will go. I will need to lay down some porch floor boards, whether or not I complete that floor now or later, also. Then, there’s more to be done so that the porch roof can be put on. And, there’s a whole lot more work after that. I’ll keep plugging away, and it’ll get done.

Wednesday, May 20, 2009

Perimeter wall footer forms started

I set out this morning to get the concrete forms for the footer that will support the perimeter block wall completed today. The first task was to get the bottom of the trench leveled off at the right depth. Because the house is on a slope, I’m not putting all of the footers on the same level. In fact, thleveling the bottom of the trenchere will be four different levels. The front of the house is about 2 feet higher above the ground than the back of the house.

Using a shovel, a grub hoe, and a grape hoe (the latter two are wonderful tools I bought from easydigging.com), I removed some dirt from the bottom of the trench where needed and added some in other places where needed. I had my boys tamp the loose dirt firmly into place. By lunch time I had made it all the way around the house.

After lunch, I started putting wooden forms in place. I drove stakes I cut into the bottom of the trench, measuring from the string I had previously strung to get the tops of them to the proper level. Then, I screwed some 2x3s onto the stakes, mforms at back of houseaking sure they were level and the proper distance below the string. The string gives me the final height for the block wall.

I was able to get the forms in the back of the house and along one side mostly completed. Along the side, I had to step down almost 8 inches in two places because of the slope. Malchiah forms on side of housejoined me after I had started working, and I put him to work tamping dirt on the outside of the forms.

Across the front of the house, there will be six courses of blocks. There are footer levels for five courses and four courses on the side while there will be only three courses on the back. I’m trying to make all of the different levels match up so that blocks could be laid continuously around the house. However, I may treat each level separately, laying blocks for each one independent of the others. They will all be surface bonded later and won’t be visible. As far as structural integrity, there should be no problem considering their purpose.

We’ll continue work tomorrow and Friday. It’ll be next week before we have the concrete delivered for the footers.  

Tuesday, May 19, 2009

Perimeter block wall footer excavation

Last evening I moved some of the top soil piled near the end of the house (it’s been piled there for six years already). I didn’t move it far – just a few feet. This was so that I would have enough room to maneuver the backhoe to the rear corner of the house and start excavating the trenches for the footer upon which I’ll build a short block wall to enclose the crawlspace. The wall will also help support the porch floor and straw bale wall.

I continued the excavation from the other corners this morning, trying to dig the bottom of the trench level. That’s easier said that done. However, it came out within a few inches over any given length.

After finishing what I could with the backhoe, I threw some dirt out of the trench with a shovel and knocked down a few high spots. After that, I stretched and leveled a string from one corner of the root cellar walls all the way around the house to another corner of the root cellar. This allowed me to get an accurate measure of my depth in order to figure how much more excavation or filling in is needed.

I plan on working on constructing forms for the footer tomorrow. It will be 14 inches wide and 8 inches in depth. After the forms are in place, I will raise or lower the bottom of the trench to ensure the thickness of the footer will be as intended. If I get this done tomorrow, I hope to have the concrete delivered Friday (I’ve got to bale hay on Thursday).

The blocks around the perimeter of the house will be dry stacked like the cellar walls. I may only surface bond the outside because there won’t be any real lateral forces on this wall. I’ll decide for sure later.

Here are some photos taken this evening of the work that’s been accomplished so far:

 

back corner  back corner toward cellar  front of houseunder mudroom

Thursday, May 14, 2009

Backfilling around the root cellar

I worked on the interior walls earlier in the week, getting three of them coated with the surface bonding cement – all but the long wall on the house side. So, yesterday, I began the process of backfilling against the walls of the cellar. It was nice to have the backhoe to use; it would’ve been overwhelming to do this job with a shovel.

I situated the backhoe behind the house near the corner of the root cellar and began moving dirt from the pile on the hill. This went fairly well. I could reach about 16 or so across the back edge. There was one problem: a few jerks with the hoe caused the bucket to slide over against one house post. I didn’t like that, of course. Initially, it wasn’t clear to me how to get it away from the house. I couldn’t back up because one rear tire was on the edge of the hole. I was able to move it without causing any damage to the house.

I was able to position the backhoe at a few different locations on either end of the cellar and put fill dirt in around almost all of the walls. I took it easy, knowing I didn’t want to knock into and mess up the walls.

On the house side of the cellar, there was about 14 feet of wall which the backhoe couldn’t reach because of the house frame. I had to use a shovel. Thankfully, the area to be filled here wasn’t to wide and didn’t need to be filled to the top of the blocks.

Here are a few photos taken after I finished today (the pvc on either end is for air vents):

house side root cellar root cellar looking down the back wall

Monday, May 11, 2009

Root cellar: surface bonding cement

We’ve had more than five inches of rain during the last nine days. In between some of the showers and storm, I’ve been able to work some on the root cellar. The frequent rain has been frustrating in that it’s kept me from getting things done like I want to, but that’s the way it goes.

The blocks are all stacked for the walls. I was able to fill 12 cores in the walls last week when we had a mostly rain-free day. I filled six more cores yesterday, all that will be filled. Last Thursday I was able to apply the surface bonding cement to the outside wall toward the hill on the back of the root cellar. That night we received some very heavy rain (over an inch and a half of it) which caused some mud to break free on the back wall of the excavation. Not too much, but I was glad to have the wall done on that side.

Today, I installed the PVC through the end walls to which I will connect the fresh-air vents for the cellar. I used concrete and mortar tooutside walls are done fix them in the wall and cover the holes around the edges.

Then, I finished parging the rest of the outside walls. It was muddy down in the hole around the outside of the cellar walls. The dirt is mostly clay and sticks to my boots like crazy. I wore my muck boots since they can be cleaned off fairly easily.

After finishing the outside walls, I changed shoes and began on the inside. I was able to parge one inside wall, an end one. I hope to finish the other three walls tomorrow.

first inside wall pargedI mixed the surface bonding cement in a wheel barrow today, using a garden hoe. It worked fairly well. Previously, I mixed it half a bag at a time in a five-gallon bucket using a paddle mixer with an electric drill. That method actually worked better, but my mixer needs repaired. So, I didn’t use it today.

The key is getting the right amount of water in the mix. If it’s too wet, it’ll slump off of the wall. If it’s too dry, it takes a lot more effort to trowel it on the wall. When it’s mixed just right, it trowels on smoothly and stays where it’s supposed to. It’s been a trial-and-error process getting the mix figured out.

Surface bonded concrete block walls look nice, I think. Better than regular, mortared block walls. It’ll be nice to see them all complete. At that point, I’ll start backfilling.   muddy boots