Introduction

The 57 acres that comprise Cedar Ridge Farm are located in the beautiful rolling hills of South Central Kentucky. My wife, our four children, and I are on a homesteading adventure as we work toward increased self-sufficiency. We grow much of our own food and enjoy being in touch with the agrarian roots of our lives.

One of the major projects we have undertaken is the building of our own home. The house we're building has three major distinguishing features: 1. we're building it without incurring any debt; 2. it is a timber frame structure; and 3. the exterior walls will be plastered straw bales. We live debt and mortgage free, and building our house with that approach makes perfect sense. Large timbers in a home possess a beauty and project a sense of strength, stability, and warmth that we want in our home. Straw bale walls provide insulation and make ecological sense. This blog is a record of our home-building project.
Showing posts with label update. Show all posts
Showing posts with label update. Show all posts

Sunday, November 21, 2010

Quick update

Having gotten the siding on the house, I was able to spend time in the woods last week. Rifle season was open here from last weekend through this one. We love venison. So, I wasn’t working on the house; 003I was out trying to harvest some meat for the family.

My dad and Danny also hunt here. We got three deer last Sunday and none since. We processed the meat – canning and freezing. We would like more, but we’re thankful for what we were blessed with. I’ll spend some more time out during our week of muzzleloader season in December.

Anne and the children and I are going to spend Thanksgiving with family in North Carolina. So, it’ll be December before I get back to work on the house. I have a lot I want to get done this winter. So, I’ll need to stay busy with it.

I’ll post more once I get back to work on the house.

Friday, February 20, 2009

More cedar logs

Dad and I cut and skidded another 21 logs out of the woods earlier this week. I should only need a few more. Currently, I'm in North Carolina my family visiting relatives. All four of Anne's sisters and brothers live in or near North Carolina (two live in SC near Charlotte, NC). After we return home early next week, there's more to do on the house projects. I'm anxious to get things done, but for a lot of it I've got to wait on the ground to dry a bit and the weather to be nice. Having a few spring-like days recently has really helped.

More to come, so stay tuned . . . .

Tuesday, December 16, 2008

This is a house blog

Some people have complained (mainly my sister and brother) that I haven't updated my blog in too long of a time. They are correct, of course. However, this is a blog about my house project. When I work on house-related projects, then I have something to post about. When I don't work on such projects, I don't have something to post about. Sure, I could post some non-related things, but I've refrained from doing so.

Over the summer and into the fall, my attentions were directed in other directions besides the house. We raise a lot of our own food, and this takes time. There were other projects to complete and limited funds to spend on the house. So, there wasn't much progress on the house. I am hoping that this will change as we progress into next year. I've made arrangements that should allow some funds to be made available for the house. My goal is to be able to move in by Thanksgiving 2009. It's an ambitious plan, but we greatly desire to realize it. Arrangements are being made that will free me from some of the food-production responsibilities so that I may devote my time to house building. So, keep your eyes on the blog in the coming months. God willing, there will be a lot of activity and progress on the house in 2009.

Since house-building is not the only thing occupying my time, I have started another blog focused on some of the everyday adventures and activities that are part of our lives here on Cedar Ridge Farm. If you're interested, you can check it out at New Kentucky Homestead. My new blog will allow this one to remain specifically a house blog.

Thursday, April 3, 2008

Just a quick update

Sorry, no photos this time. I just wanted to provide a quick update on what I've been doing the last few days.

Last Friday we made a trip to Lowes to buy some rebar for when we pour the footers and root cellar floor. We also bought some 3" pvc for the drain line from the root cellar. While I was loading the rebar, Anne noticed a "damaged" one-piece tub/shower unit sitting outside that was marked down to $50. It had a small hole in the tub edge and some small cracks in the acrylic of the bottom, both of which I should be able to patch fairly well. So, I offered $25 which was accepted, and we have our second tub/shower unit. We spent less than the price of one for two, because the first one we bought a few months ago was marked down because of slight damage that won't even be visible once it's installed.

Sunday was a nice day since the predicted rain didn't show up. With the backhoe, I dug an 80 foot long trench for the drain line. This is for a floor drain in the cellar. At the end near the cellar, the trench was nearly 8 feet deep. It ended up at 2 feet deep at the other end because of the slope. This provides about 30 inches of drop over the 80 feet. My boys helped glue the 3" thinwall PVC together and put it in the trench. Then, I used the backhoe to fill in the trench.

Yesterday, I dug up a culvert on the drive going to my barn. The one there just wasn't big enough to handle the amount of rain water that washes through there on days like today (it's raining right now). I had some eight foot long 12" concrete culvert sections that I had dug up previously. I was able to put two of them end to end (they have a bell end for connecting them) and one of the 6 inch PVC culverts I dug up back in place. It should help keep the runoff from flooding across the drive.

I also planted 1/2 acre of wheat yesterday afternoon. It was dry enough so that I could disc the field last week, then we received about 1/2 inch of rain. It was dry enough yesterday that I could run the disc over the field one more time. Then, using my hand-powered broadcast seeder, I spread 100 pounds of hard red spring wheat over the ground. Then, I ran a friends cultipacker over it to help push in into the ground a little. With the rain we're getting today and will get tomorrow, it should be sprouting soon!

Today, I've been calculating the number of concrete blocks I need to acquire to complete the foundation walls and root cellar walls. I have 238 blocks I've already collected. I need another 750 or so. I'll also need to order six yards of concrete for the footers and floor once I have everything ready. That'll be after it dries out a bit. It's spring and is still wet here.

Monday, October 22, 2007

Eye injuries and the Great Smoky Mountains

Alas, it has been several weeks since I last posted to my blog. It was a lot of work getting ready for the raising and then getting the frame completely assembled after the work on Labor Day weekend. It was great though! I had as my goal to get the roof on before the end of September. At least in the theoretical sense, it was an achievable goal. However, it didn't happen. I can explain why, of course.

In order to get the roof on, I needed to do several things. First was to get the boards for the cathedral ceiling prepared. This involved edging the boards I already had planed and cutting a rabbet on the edges in order to lap joint them on the frame. After that was completed, I needed to build a framework to hold the metal roof at least 14 inches above the ceiling boards (gotta have room for the blown in cellulose insulation). Then, the metal roof could be put on. So, naturally, I started at the beginning by beginning the work on the ceiling boards.

At this point let me offer some important advice: when using a table saw, wear eye protection.

I had barely begun the process of edging the ceiling boards when I wished I had taken my own advice. A piece of board chipped off of the edge and hit me squarely in my left eye. Had I been wearing the eye protection I knew I should be wearing, I would've been fine. But, I wasn't. My eye was injured. It hurt. A noticeable indentation or scratch (corneal abrasion) was left across the pupil of my eye and my vision was blurred because of it. Since my left eye has been my dominant eye, the blurred vision affected what I felt comfortable and safe doing. Driving and using the table saw were two things I wasn't comfortable doing for a couple of weeks after the accident. Currently, six weeks later, my vision is still affected, but I have adjusted so that I am able to do things that I did not feel safe doing in the first couple of weeks after the incident.

So, I didn't get very far on the roof. Then, at the end of September, my family and I left for a week long visit to the Great Smoky Mountains National Park. We rented a house and spent a week there three years ago, and the children have wanted to go again. So, we saved some pennies and did so. We stayed in a nice house near Cosby, TN, which we rented through Smoky Dreams Cabins (very nice). We visited several areas of the park and walked a few miles on trails to see some of the old buildings they've preserved in the park. We had a great time.

Here are three photos from our trip:





Friday, August 24, 2007

Update: 9 days until the raising!

The hot and humid weather has continued all month. We haven't had any rain in August and we've been over 90 degrees every day so far. Yet, we've continued our work in preparation for raising day.

We completed the assembly of the final bent on Tuesday, August 14. We then began on floor joists. For them we're cutting the dovetail tenon and decorative arc on one end. The other end will be completed after exact measurements are taken once the frame is erected. We finished all of the floor joists (59 total) and the purlins (37 total) on Thursday, August 23 (yesterday). We also built the gin pole on Wednesday of this week. It's about 16' tall with a 7' base. I still want to do a bit more with it early next week before getting it put into place.

When doing the fit-up and assembly, a tenon on one collar tie broke. So, I needed to replace that. I completed that replacement yesterday, also.

So, at this point, the frame is ready to be raised! It's kind of amazing to have all the timbers ready. It's taken a full 2.5 years to get all the joinery and fitting-up done. I'm not complaining. I really haven't worked on it continuously throughout that time. There were some weeks and months when I didn't complete any of the joinery because there were other things that needed done.

I'm looking forward to seeing the frame standing in place. I'm not sure what all I will feel when it's up, but I imagine there will be several emotions. It's gonna be great, though!

Sunday, July 15, 2007

Update and thoughts on raising the frame

On Thursday of last week (7/12/07), I was able to fit up the back wall of the frame. Mark the Intern helped. This involved fitting together 4 posts, 6 girts, and 6 braces and drilling the holes for the pegs. It went together quite well. However, I forgot to take the camera, so no pictures. It looked a lot like the pictures from earlier, though. It's really neat to see what I've been working on for over two years actually begin to take shape.

I'm contemplating raising the frame. Basically, I'm trying to get it straight in my head how it'll be done. I'm not planning on renting a crane to do the job. Yeah, a crane would probably make things easier, but it would also create its own challenges. I think that with enough help and a gin pole, we can get the job done safely and relatively easily. I've never done this before, so I might be wrong.

One of my intentions at this point is to raise each bent completely finished, including the rafters. Because of the design of the bent, the weakest point will be where the rafter and two posts attach to the tie beam. The only thing holding them will be 2"x4" mortise/tenon joints. My idea is to securely clamp three 6"x6"s or 6"x8"s on the back of the bent. These will be long enough to be attached to the lower beams, the tie beam, and the rafters. Then, when raising the bent, I will pull on these braces, not the bent itself. They will hold the bent rigid while they take the stress of the raising.

The gin pole I have in mind is what is called a pair of 'shear legs.' It's basically an A-frame of two poles. I 'borrowed' the picture at the right from The Mountain School. I'll probably use a couple of cedar trees since I have a lot of those here, and they'll be relatively straight and long enough. Long enough for my uses will be 25-30 feet. I won't have to lift more than 22 feet. The shear legs feet are securely anchored so they won't move. I'll probably set them in a couple of holes and chain them to a couple of my foundation piers. It'll also be secured by lines to anchors or trees toward the back. In barn raising from this photo, they used a block and tackle rigging and raised their bents with human power. I'm planning on using a tractor to supply the power to raise the bents.

I'll continue pondering on the raising. I want it to go well, smoothly, and relatively quickly. It'll be an exciting day, I'm sure. I don't know when it'll be yet, but I'll be sure to announce it and invite lots of help!