The 57 acres that comprise Cedar Ridge Farm are located in the beautiful rolling hills of South Central Kentucky. My wife, our four children, and I are on a homesteading adventure as we work toward increased self-sufficiency. We grow much of our own food and enjoy being in touch with the agrarian roots of our lives.

One of the major projects we have undertaken is the building of our own home. The house we're building has three major distinguishing features: 1. we're building it without incurring any debt; 2. it is a timber frame structure; and 3. the exterior walls will be plastered straw bales. We live debt and mortgage free, and building our house with that approach makes perfect sense. Large timbers in a home possess a beauty and project a sense of strength, stability, and warmth that we want in our home. Straw bale walls provide insulation and make ecological sense. This blog is a record of our home-building project.
Showing posts with label concrete. Show all posts
Showing posts with label concrete. Show all posts

Wednesday, June 2, 2010

Footers and piers

With the return of warmer and drier weather, I’m able to get back to working on the house. There are a lot of different projects vying for my attention, but the urge to get this house done so that we can move in by next summer is upon me. I really want it finished. It is within reach.

I have worked on a related project during the last few weeks: a cistern to catch rain water. The cistern is located in the shed section of the garage which is near our current home which is at the top of the hill. We’ll harvest rain water off of the garage roof. I’ll run a 1.5 inch water line down to the house which is 50 to 60 feet lower in elevation. This should provide at least some of our water pressure. Later, I will build a cistern to harvest rain water off of the house, too. We will not hook up to city water.

We also will not hook up to the grid for electricity. We are currently using a solar electric system that I put together and installed. When we move into the new house, I’ll re-install the system for it.

We also decided to not put in a septic system. We’ll use sawdust toilets and compost it. You can read about this system in the Humanure Handbook. It’s simple and effective. It turns a waste into a resource.

Sometime at the end of last year, we changed one part of our house design. The kitchen extend out from the frame into part of what would have been the porch near the corner of the house. It will extend out 9 feet and be 12 feet wide. This will make it a non-traffic area and allow there to be a door off of the main kitchen into what will be the summer kitchen.

In order to affect this change in the design, I have to build a block wall to enclose the crawlspace under the kitchen. The space under summer kitchen will not be enclosed with block. The summer kitchen will actually be an enclosed portion of the porch on the corner toward the barn. I will probably use some cement board to enclose underneath it later on.

Last week, I started digging for the footer for the kitchen crawlspace wall and for the footers that will be under the piers that will support the porch. Actually, I had help. My good friend Jon is working with me two days a week this summer, and he helped with the digging. Having Jon working with me keeps me more focused and on task because I want to be sure and have plenty to keep him busy on the days that he’s here.

We finished excavating with shovels for all the footers last Monday. On Wednesday when he came over, I was ready with 100 80-pound bags of concrete mix that I bought on Tuesday. It probably wouldn’t have cost any more to have the local concrete company send a truck out, but with the landscaping changes I made last summer/fall, there really wasn’t any way that the truck could have gotten close enough to pour the footer.

I do have an electric powered concrete mixer that I bought several weeks ago in anticipation of the material that will need mixed. It’s one that Lowes offered, and it’s worked quite well the times we’ve used it. On Wednesday, we set it up near the house (powered by my generator since I had the temporary power disconnected) and began mixing. Two bags fit in it quite well. It took 54 bags to complete the footer for the kitchen.

For the porch pier footers, we moved the mixer so that it set right over each hole. We mixed three bags at a time which is all that would fit in the mixer. It had no problem mixing that amount of material, and the generator never complained. After mixing, we dumped the concrete directly in the hole and moved to the next one.

Everything went very smoothly, and we finished all of the block mortared onto footerconcrete work by the end of the day. We had two bags left over which will be used elsewhere later on.

This week Jon wasn’t able to be here on Monday. So, I worked on my own. On Friday I had purchased some 12” concrete blocks for the porch piers. They didn’t have any surface bonding cement in stock – I’ll need that for surfacing the kitchen crawlspace wall.

I put strings up to make sure that I would have everything lined up properly.  Then, I set out the blocks for the kitchen wall in preparation of first course for kitchenmortaring the first course onto the footer. After that, I mortared each block, making sure it was level.

Once I finished the first course for the kitchen, I measured for the porch piers to make sure they would be properly situated on their footers. While doing this I discovered something interesting in a very good way: the distance from the corner of the porch to the block wall for the kitchen was the same distance as from the rear corner of the porch to the root cellar wall – 33.5 feet. First blocks for porch piers at back of house I was kind of amazed because the way it’s put together, there was no reliable way to ensure that it would be so.

I was able to get all of the first blocks for the porch piers mortared into place and level yesterday. Today, after returning a piece of equipment to a friend, I started stacking blocks. I started with one corner  of the porch. Mortared block pier After stacking the blocks, I decided that I would mortar the blocks together. I was going to dry stack them. I’ll stucco the piers later so they will match the rest of the foundation walls.

By the time I quit this afternoon/evening, I had all of the piers across the front of the house mortared. These are the ones with the most blocks. It shouldn’t take too long to mortar the blocks for the other piers tomorrow. Jon should be here tomorrow, and I’ll have him start dry-stacking 033the blocks for the kitchen.

I hope that the work can go fast and furious from here on. That should make it possible to keep the blog updated much more regularly.

Thursday, June 18, 2009

Blocking in the crawl space

We’ve had plenty of rain so far this year. The garden has not suffered from dryness. In between rain showers and storms and all the other work there is to be done around here, I have continued to work on the house. I laid out blocks on the footer last week, figuring where the crawlspace walls need to be in relation the house frame.

011Earlier this week, after some rain and before some other rain, I started mortaring the first course of blocks on the west side of the house for the wall that will be under the mudroom. The first step in the process was to remove some of the accumulated mud that had been deposited around the blocks by the rain. Then, I lifted out the block that was to be mortared into place, and placed some mortar where the block had been.

012After distributing the mortar where the bottom edge of the block would set on it, I placed the block back into position. The main purpose for the mortar is to get the first course of blocks level. So, after placing the block on the mortar, I used a piece of wood to get it into place and then checked its placement with a level. I endeavored to make sure that each block was level side-to-side and along the line with the other blocks.

016015

It takes a while to mortar the first course of blocks into place. I was able to complete the ones on the level that will be beneath the mudroom.  It then rained off and on during the next couple of days, and I managed to work on some other things that needed done.

018

I was able to return to the project yesterday afternoon after spending the morning working on my class (I teach a class online for a university). I started by mortaring the blocks along the next level of the footer on the west side of the house. This is a shorter run than the previous level, and it went fairly quickly.

After getting these blocks mortared into level, I began laying blocks. One thing about dry stack concrete block construction is that the block-laying goes quickly. I had to haul the blocks from where I had the block company put them a few weeks ago which is maybe 20 yards away and down hill from the house. I moved six at a time using a wheel barrow. That seemed to work better than using a hand truck.

I began laying blocks for the walls under the mudroom since that mortar was fully set up and cured. After completing laying those, I went ahead and laid the ones on the section I had just mortared. I figured that the mortar wasn’t going to settle or move with the weight of the blocks anyway.

Because of the way I designed and poured the footer, there are four levels for the blocks around the house. I did not worry about making the steps for each level perfect with the other levels so that the blocks could 026be laid seamlessly all the way around the house. Each level can be constructed as a separate wall. Any gaps that may exist between levels will be filled with concrete. Then, the whole thing will be coated with surface bonding cement. I will cut cedars for the sill on top of the wall, so any variation in height will be accounted for in the dimensions to which I cut them. This simplified the figuring and block laying for me.

I saw a block wall a couple days ago for which the footer appeared to have been poured on an angle matching the slope of the house site. The blocks appeared to have been cut along the bottom so that the top would be level. I didn’t want to do that much cutting. I think my method will work all right.

025In anticipation of plumbing that I’ll do later, I cut a hole in one block before laying it. This hole will allow me to run the sewer pipe to the septic tank through the wall. I am not completely sure where the septic tank will go at this point. So, I’ll cut another hole on the opposite side of the house, too, just in case I need to place it on that side. I knew I didn’t want to cut a hole later.

022As can be seen in the photo to the left, I didn’t lay out the end wall on the cellar exactly right. It doesn’t line up straight with the crawlspace wall I just laid. I can’t change it, of course, and it really won’t create much problem. I expect that it won’t be very noticeable later anyway.

A thunder storm rolled through just after I started writing this post. I was planning on working on the front crawlspace wall this afternoon. It may be too muddy now. I’ll see in a little while.

 

      021  024033

Tuesday, June 2, 2009

Perimeter footer

With enough rain-free weather, I was able to complete the forms for the perimeter footer on Tuesday of last week. There are four levels for the footer because of the slope of the house site. I didn’t want to excavate the trench for the footer the same depth all the way around the house.

footerOn Wednesday morning, I called the local ready mix concrete company to order four yards of concrete. They were able to bring it out right away. It didn’t take long to pour the concrete. Dad and I screeded it which also didn’t take long. The footer is 14 inches wide, 8 inches thick, and has two 5/8” rebar pieces in the middle.

About an hour after we finished, a small rain storm came through. It didn’t dump much rain, but what rain that did fall fell hard. The concrete hadn’t had enough time to set up hard enough not to be affected by the rain. exposed aggregate because of rainThe main effect was that some of the cement and sand on the surface was washed away, leaving the courser aggregate exposed and loose on top. This occurred most dramatically to the footer at the front of the house because the runoff from the roof on that side hit directly on the outside quarter of the footer. You can see in the photo to the right the effect it had. It won’t really matter, though. The first course of blocks will be set onto the footer with mortar, and, once the walls are finished, the footer will be covered with dirt, never to be seen again.

footerfooter

I will begin laying the blocks this week as time allows. There are a lot of other jobs to be done around our homestead and we’ll be having some visitors for part of the week and next weekend (one of Anne’s sisters and her family).

Looking ahead to the order of construction, once the blocks are laid, it will be time to start framing the porch. I’ll have to pour footers for under the porch posts, lay blocks for the piers, and frame the porch deck. At that point I will put down the first floor subfloor, including under where the straw bales will go. I will need to lay down some porch floor boards, whether or not I complete that floor now or later, also. Then, there’s more to be done so that the porch roof can be put on. And, there’s a whole lot more work after that. I’ll keep plugging away, and it’ll get done.

Wednesday, May 20, 2009

Perimeter wall footer forms started

I set out this morning to get the concrete forms for the footer that will support the perimeter block wall completed today. The first task was to get the bottom of the trench leveled off at the right depth. Because the house is on a slope, I’m not putting all of the footers on the same level. In fact, thleveling the bottom of the trenchere will be four different levels. The front of the house is about 2 feet higher above the ground than the back of the house.

Using a shovel, a grub hoe, and a grape hoe (the latter two are wonderful tools I bought from easydigging.com), I removed some dirt from the bottom of the trench where needed and added some in other places where needed. I had my boys tamp the loose dirt firmly into place. By lunch time I had made it all the way around the house.

After lunch, I started putting wooden forms in place. I drove stakes I cut into the bottom of the trench, measuring from the string I had previously strung to get the tops of them to the proper level. Then, I screwed some 2x3s onto the stakes, mforms at back of houseaking sure they were level and the proper distance below the string. The string gives me the final height for the block wall.

I was able to get the forms in the back of the house and along one side mostly completed. Along the side, I had to step down almost 8 inches in two places because of the slope. Malchiah forms on side of housejoined me after I had started working, and I put him to work tamping dirt on the outside of the forms.

Across the front of the house, there will be six courses of blocks. There are footer levels for five courses and four courses on the side while there will be only three courses on the back. I’m trying to make all of the different levels match up so that blocks could be laid continuously around the house. However, I may treat each level separately, laying blocks for each one independent of the others. They will all be surface bonded later and won’t be visible. As far as structural integrity, there should be no problem considering their purpose.

We’ll continue work tomorrow and Friday. It’ll be next week before we have the concrete delivered for the footers.  

Tuesday, May 19, 2009

Perimeter block wall footer excavation

Last evening I moved some of the top soil piled near the end of the house (it’s been piled there for six years already). I didn’t move it far – just a few feet. This was so that I would have enough room to maneuver the backhoe to the rear corner of the house and start excavating the trenches for the footer upon which I’ll build a short block wall to enclose the crawlspace. The wall will also help support the porch floor and straw bale wall.

I continued the excavation from the other corners this morning, trying to dig the bottom of the trench level. That’s easier said that done. However, it came out within a few inches over any given length.

After finishing what I could with the backhoe, I threw some dirt out of the trench with a shovel and knocked down a few high spots. After that, I stretched and leveled a string from one corner of the root cellar walls all the way around the house to another corner of the root cellar. This allowed me to get an accurate measure of my depth in order to figure how much more excavation or filling in is needed.

I plan on working on constructing forms for the footer tomorrow. It will be 14 inches wide and 8 inches in depth. After the forms are in place, I will raise or lower the bottom of the trench to ensure the thickness of the footer will be as intended. If I get this done tomorrow, I hope to have the concrete delivered Friday (I’ve got to bale hay on Thursday).

The blocks around the perimeter of the house will be dry stacked like the cellar walls. I may only surface bond the outside because there won’t be any real lateral forces on this wall. I’ll decide for sure later.

Here are some photos taken this evening of the work that’s been accomplished so far:

 

back corner  back corner toward cellar  front of houseunder mudroom

Monday, May 11, 2009

Root cellar: surface bonding cement

We’ve had more than five inches of rain during the last nine days. In between some of the showers and storm, I’ve been able to work some on the root cellar. The frequent rain has been frustrating in that it’s kept me from getting things done like I want to, but that’s the way it goes.

The blocks are all stacked for the walls. I was able to fill 12 cores in the walls last week when we had a mostly rain-free day. I filled six more cores yesterday, all that will be filled. Last Thursday I was able to apply the surface bonding cement to the outside wall toward the hill on the back of the root cellar. That night we received some very heavy rain (over an inch and a half of it) which caused some mud to break free on the back wall of the excavation. Not too much, but I was glad to have the wall done on that side.

Today, I installed the PVC through the end walls to which I will connect the fresh-air vents for the cellar. I used concrete and mortar tooutside walls are done fix them in the wall and cover the holes around the edges.

Then, I finished parging the rest of the outside walls. It was muddy down in the hole around the outside of the cellar walls. The dirt is mostly clay and sticks to my boots like crazy. I wore my muck boots since they can be cleaned off fairly easily.

After finishing the outside walls, I changed shoes and began on the inside. I was able to parge one inside wall, an end one. I hope to finish the other three walls tomorrow.

first inside wall pargedI mixed the surface bonding cement in a wheel barrow today, using a garden hoe. It worked fairly well. Previously, I mixed it half a bag at a time in a five-gallon bucket using a paddle mixer with an electric drill. That method actually worked better, but my mixer needs repaired. So, I didn’t use it today.

The key is getting the right amount of water in the mix. If it’s too wet, it’ll slump off of the wall. If it’s too dry, it takes a lot more effort to trowel it on the wall. When it’s mixed just right, it trowels on smoothly and stays where it’s supposed to. It’s been a trial-and-error process getting the mix figured out.

Surface bonded concrete block walls look nice, I think. Better than regular, mortared block walls. It’ll be nice to see them all complete. At that point, I’ll start backfilling.   muddy boots

Tuesday, May 5, 2009

Mixing concrete & filling voids

It’s been raining a fair bit since last Thursday, making work on the house more difficult. I was able to finish stacking all of the blocks (490 of them) before the rains settled in.

Today, we had a break from the rain, but more is forecast for tomorrow along with the possibility of rain every day for the rest of the week. So, I took the opportunity to continue working on the root cellar. The project for today was to fill some of the voids in the block walls with concrete.

In all I mixed 22 bags of concrete mix (80# each) and filled 12 cavities. Each one has a length of 5/8” rebar embedded in it the full height of the wall. At the bottoms of most of the filled cavities, there is 18” of rebar that is embedded in the footer. At the top of each fill, I’m placing a 1/2” j-bolt/concrete anchor with which to bolt on a wood sill. I will mill the sill out of cedar, and it will be 4-1/2” thick – this brings the height of the wall even with the bottom of the first floor girts.

Today’s work went well. The biggest problem is the mud. This is some sticky mud because of all the clay in the soil where I’m working. I wore muck boots and didn’t worry about the mud mess.

With more rain forecast for tomorrow, I don’t know if I’ll be able to get back to the project for a couple of days. I still have the surface bonding cement to trowel on to the walls which I’ll start as soon as I can.

Wednesday, April 29, 2009

Dry stack concrete block construction

While doing some research about laying blocks in anticipation of building our root cellar, I came across drystacked.com and thenatualhome.com. I also found a U.S. Dept. of Agriculture bulletin entitled Construction with Surface Bonding. This information convinced me to use this method.

Today, I had opportunity to actually experience dry stacking concrete blocks. Having set the first course in mortar on the foundation yesterday, making sure it was level, allowed me to get a lot of blocks put into place. As I stacked each block today, I checked it for level along and across the wall. corners stackedOften, when it was out of level across the block, just turning the block around brought it back in the bubble.

I started on the corners, stacking the four corners to five blocks. Then, I set blocks belunch timetween the corners until I had the walls built up to five courses by lunch time. Some of the last blocks on a side took a little persuasion to get to slide in, but they all went.

I’m building my root cellar walls ten courses high. By the time I stopped today, I had two walls at ten courses, one long wall at seven courses, and the other short wall ten courses at one corner and eight at the other corner.

quitting time

Along the wall near the house, I applied the surface bonding cement (Quikrete Quikwall) on the outside of the blocks. I won’t be able to get behind this wall to do surface bonding cementit later. So, after laying the first four courses, I leaned over and troweled it on. After laying three courses, I added more above what I’d put on before lunch. Based upon how this bit went on, I think surfacing the rest of the walls shouldn’t be too difficult.

Dry stacking the blocks was simple enough that even Jessica helped. She came to see what I was doing this afternoon and wanted to help. I showed her how to check level on each block and how to put them on the wall. She worked for a while and set several blocks.

Tuesday, April 28, 2009

Root cellar: starting to block the walls

Another post on the root cellar? Well, that’s the part I’m working on until I get it far enough to work on the next thing.

The floor turned out nice. I took the plastic and tarp off of it Monday. The plastic kept moisture on the surface while it was curing. This was good since I don’t have a hose near the site I could’ve used to mist it. I’m pleased with how the floor turned out. It’s smooth enough to be easily swept.

Last week I ordered and paid for enough concrete blocks, mortar mix, surface bonding cement, and concrete mix to complete the root cellar and crawlspace perimeter (if I figured correctly). 5 cubes of blocks stacked in the root cellarYesterday afternoon the first load was delivered which included six cubes of blocks (90 blocks per cube) and most of the bags of mixes. The rest of my order is scheduled to be delivered next Monday.

Dad helped me stack five cubes on the root cellar floor after they were unloaded from the truck. That was 450 blocks – approximately 16,200 pounds worth that we moved. We were able to set up a ramp down which we slid the blocks one at a time into the root cellar.

Today, I began the root cellar walls. I’m dry-stacking the blocks. This methods involves setting the first course of blocks in mortar onfirst course the foundation, no mortar between blocks. Then, the blocks are stacked without mortar in succeeding courses. Once they are stacked, some of the cores are filled with concrete and rebar for additional strength, after which both surfaces of the walls are coated with surface bonding cement. This makes a strong, durable wall. It’s also a little easier for the novice builder who isn’t a mason.

By the time I finished this evening, I had the first course set. first course mortared into placeIt is important for this course to be level – that’s the main reason for the mortar, actually. After I double-checked my measurements, I laid out the blocks for the first course. I checked for square and that everything lined up. Then, I began to move the blocks again, mix mortar, and set them, checking and double-checking for level in every direction. Tomorrow, if the weather is nice enough, I’ll begin dry stacking blocks on top of the first course. In all there will be ten courses. I may mortar after the fifth course just to ensure things are level, but I’ll hold off on that if it’s not necessary.

 019

Friday, April 24, 2009

Root cellar: the floor is poured

The ready-mix truck arrived about 8:30 this morning with 4.5 yards of concrete for the root cellar floor and footers. I figured it would be simplest to do a monolithic pour rather than separate pours for footer and floor. Besides, doing so would’ve involved smaller batches of concrete and extra hauling fees ($75 if I received less than 4 yards at a time).

ready-mix truckconcrete pourThe driver was able to get the truck right up to the edge of the root cellar excavation and pour it all from one point. I had made sure ahead of time that there would be access from two different sides so that the driver could decide the best point(s) for unloading the concrete. It took less than 15 minutes to dump the concrete into the forms. I then spent five hours finishing it.

The excess concrete was not very much, and it was screeded over the forms at the far end of the pad. My dad helped spread the concrete as it was unloaded from the chute on the truck and then helped me with the screeding.

small bull floatbig bull floatI constructed two bull floats for floating the surface of the concrete after it was poured. They worked well for this purpose. One was made out of an old mop, a board screwed to it’s end, and an extra handle attached. The other used a 10 foot long piece of 1/2 tubing and a larger board attached to its end.

rebar insertedI inserted sections of rebar with a J-bend into the concrete along the back wall and the side walls. These are spaced to fit within some of the block cavities. In these cavities, I will insert more rebar once the walls are up and fill them with concrete. I’m going to dry stack the concrete blocks and then use surface bonding cement on both sides. This method is supposed to be stronger and easier for a novice than traditional mortar masonry.

troweled surfaceOnce the concrete set up enough, I was able to trowel the surface to smooth it out. This went quite well. The cellar was in shade while the concrete was poured and floated. Then, the sunshine worked its way across the floor gradually. The area in the sunshine set up faster while that in the shade took longer. This was good because it gave me plenty of time to trowel the surfaces that were drying faster rather than having the whole thing setting up about the same time.

tarped slabAfter finishing with the trowel, I covered the slab with plastic and an old tarp so that I won’t dry out too fast and will hopefully cure better than it would otherwise. I’ll leave it alone until Monday or Tuesday. The blocks for the walls are scheduled to be delivered Monday afternoon. So, if the weather permits, I may be able to start laying some block on Tuesday.       

Thursday, April 16, 2009

Root cellar: concrete forms in place

Although it was overcast this morning, it didn’t rain today. The sun finally came out from behind the clouds around noon. I worked in the hole all day. This morning the damp clay in and around the work area stuck to my shoes all the time. With the sun out this afternoon, I didn’t have any stick. Either the sunshine dried things just enough or this clay is allergic to sunshine.

I didn’t use the backhoe today. I moved a fair bit of dirt with a shovel and a grape hoe, though, in order to get make sure the bottom of the Salvaged boards for formshole was level. It was close, thankfully. There was some dirt along the edges that needed moved so I could set the forms.

For the forms, I used some boards Danny salvaged from an old mobile home he helped demolish. They are fat 2x4s, measuring about 1-3/4” x 4-1/4”. I had to pull some old staples out of them, and then I was ready to set them in place. I also cut some stakes from some scrap boards I had near the house.

I started in one corner and leveled the forms from there. One end formed by lunch timeBy lunch time I had one end and over half of both of the long sides done. Since it’s important to put the outside corner of the root cellar walls in the right place, I had to take some measurements from the west side of the house. Determining the precise location of this corner is somewhat difficult. However, using a ladder strapped to the floor joists in the house, I was able to measure eleven feet out from that side of the house and set a stake at the inside corner of the root cellar.

To figure the outside corner, I measured from the stakes I had set previously. It soon became apparent that I didn’t have things laid out square. It was time for lunch at that point, so I left it till this afternoon. Armed with an exact measure of the hypotenuse of a right triangle with two eleven foot sides and a framing square, I adjusted one of the corners on the forms I had already set. Once I did that, the diagonal measurements came out correct – things were square.

It didn’t take long this afternoon to finish the forms. I built a small box to go around the floor drain. I’m not sure exactly what the usual way is for pouring a floor with a drain. I figure that I can pour everything around and up to the form around the drain with enough slope for water that ends up on the floor to head for the drain. Later, I’ll cut the drain pipe at the right level, mix and pour some concrete, and fill the last section of the floor around it.

Forms in place

The next step is to dig a couple inches deeper near the forms for the footer and lay out some rebar in the footers and floor. I don’t think that will take too long. Once that’s done, we can have the ready mix truck come out. The only thing that may interrupt the timing of things is rain. If we get too much rain, I’ll have to wait for things to dry out before the concrete truck can get close enough to the hole. I hope the weather cooperates so we can pour the concrete next Tuesday or Wednesday.

Root cellar: second excavation

On Monday I had a neighbor haul a friend’s backhoe to our place. This is the same backhoe I used a year ago to excavate the root cellar. Since I didn’t get the floor poured and walls built last summer, the winter rains washed a lot of dirt and debris into the hole. I started shoveling it out by hand, but found the task daunting. The backhoe has saved a lot of time.

I was able to move clay-dirt from one pile near the hole on Monday, but then it began to rain. I didn’t work with the backhoe on Tuesday, but yesterday I was able to get at it. It was a little muddy on top still, but I wanted to get the job done.

Today, I plan on finishing with a shovel, moving the dirt left in the hole out of the way. Then, I will begin building the forms for the concrete. If the weather cooperates, we’ll pour and finish the floor next week.

Tuesday, April 14, 2009

Milling porch posts (part 2 with video)

Sunday of this week was a nice day. Dad and I had already milled 15 6x6 posts for the porch, and I decided to get the rest of them milled. Last week I 3 new Oregon saw chains from from Treestuff.com (3/8” pitch, .058 gauge, 115 drive links). They shipped them out right away and I received them on Friday. These were regular cross cut chains with a 25 degree angle on the teeth. Sunday morning I ground the first one to 20 degrees with a 50 degree hook angle. Generally, ripping chains are ground to either 0 degrees or 10 degrees. I wanted to try it at 20. It worked fine. I’ll probably try the next one at 10 degrees so I can compare it to this one.

I purchased a new video camera (Canon FS100) for creating a video documentary of the house-building process from this point forward. Using the sawmill provided an opportunity to use it. My dad shot this video of me finishing one of the posts.

I’ll probably share occasional videos on the blog. The editing process for the documentary of the project will happen later.

After milling on Sunday, we now have 22 posts ready for the porch.

cedar 6x6s cedar 6x6s cedar 6x6s

I still have some more cedar logs to mill, but I’ve not decided yet what dimension lumber/beams would be most desirable at this point. I’ll also need to haul some beech logs from Gill’s place and mill them. I think the milling will be put on hold for the next three weeks at least, though. I’m hoping to get the root cellar floor poured and the walls blocked and then to get a perimeter of concrete blocks laid around the timber frame. These will enclose the crawl space and help support the porch and straw bale walls.