The 57 acres that comprise Cedar Ridge Farm are located in the beautiful rolling hills of South Central Kentucky. My wife, our four children, and I are on a homesteading adventure as we work toward increased self-sufficiency. We grow much of our own food and enjoy being in touch with the agrarian roots of our lives.

One of the major projects we have undertaken is the building of our own home. The house we're building has three major distinguishing features: 1. we're building it without incurring any debt; 2. it is a timber frame structure; and 3. the exterior walls will be plastered straw bales. We live debt and mortgage free, and building our house with that approach makes perfect sense. Large timbers in a home possess a beauty and project a sense of strength, stability, and warmth that we want in our home. Straw bale walls provide insulation and make ecological sense. This blog is a record of our home-building project.
Showing posts with label brick. Show all posts
Showing posts with label brick. Show all posts

Monday, October 24, 2011

First smoke–building the chimney part 2

After getting started on the chimney nearly a month ago, I continued to work on it as the weather permitted and as I had time. The first day on my own, I was able to install the thimble where the stove pipe will connect on the inside, and I was able to continue above it a few courses. The next day required cutting a hole in the roof and extending the chimney above the house.

I was able to take the chimney high enough above the roof that day so that I could flash around it, just in case it decided to rain. For flashing, I used aluminum flashing material that I already had. I put a piece across the front, pieces up each side, and a piece across the back of the chimney. Also, when laying the bricks, I etched the mortar for step flashing on the sides and for the flashing on the back. 003Based upon a recommendation, I used polyurethane caulk to seal the edges of the flashing and underneath it.

As the chimney continued to build high, it became necessary to set up scaffolding in order to keep it going. I nailed some 2x8s together, leveled up this framework on the roof in front of the chimney, tied it to the portion of the chimney already constructed so that it couldn’t slip out of place, and set up a section of scaffolding on top. This worked out very well. I was able to build the chimney nine feet above the roof with this one section of scaffolding.

I debated making the chimney only 7 feet above the roof, but finally decided on going the full 9 feet.009 I figured it would be easier to add the extra section of liner and bricks now than it would be to do it later on if it became necessary.

Finally, on October 11, I finished the chimney. It is 20 feet tall, extending from first floor level in the house (it stands on its own foundation). On that day, I laid 14 courses of brick and capped it with mortar around the last few inches of the clay liner. I took down the scaffolding, finished the little bit of flashing that I hadn’t completed (some step flashing on the east side), added a little more polyurethane caulk, and took some photos.

 

016024

 

 

 

 

 

 

 

 

 

At the end of last week, Dad and Danny helped me get the wood stove I’ve had in the garage for the last several years (it’s one we heated our current home with for a couple of winters after we first moved here) into my truck and on the porch of the new house. Today, Ramiah cleaned the stove. So, this afternoon, I took it in the house and connected it to the chimney.

With the stove hooked up, I decided to build a small fire to inaugurate the chimney. So, this evening, we had first smoke in the new chimney. It was exciting!

016029

Wednesday, September 21, 2011

Building the chimney (part 1)

013Yesterday, a good friend came over to help me begin building the chimney for the house. Previously, I poured a footer and built a block foundation for it, but I hadn’t started on the actual chimney yet. Although I’ve read a little about how to lay brick, I wasn’t quite sure about tackling the project by myself. So, I asked David if he would help since he has laid brick on many different jobs in the past. He was glad to assist.

David showed me the basic technique, which for this job is not too difficult. I’ve laid a few concrete 003blocks with mortar in the past, and this brick work was easier, as far as I’m concerned. The biggest concern is keeping things level and plumb as it goes up. We used levels to check things on each course. My biggest concern is going straight up to the hole I have cut in the ceiling through which the chimney is supposed to go. We seem to be on line for that.

We put a clean out access door near the floor. I’m not sure how the door I bought for this purpose was intended to be attached, but we figured out how to get the job done.

The thimble for the stove pipe coming from the stove will be just above the narrow window which is on the wall that will be behind the stove. 014By the time we finished yesterday, we were at that level which is about seven feet off of the floor, having set the flue liner with the hole for the thimble.

I’ll finish the chimney during the next couple of weeks, depending on the weather. It’s been kind of wet here for a few days which isn’t good for laying brick outside. I’ll need to push it through the roof next,028 so I will be working on the outside. It’ll be interesting laying the bricks as the chimney goes through the ceiling and roof area, but I’ll manage.

I’m happy with how it’s looking. I bought these bricks mainly because the brick place was selling them at clearance price, trying to sell their remaining stock. I ended up buying them for less than 15 cents apiece (less than half price). However, seeing them as they become a chimney, I like how they look really well. It’s going to be a nice looking chimney.